What is the clean room schedule? What principles should be followed in preparing a clean room schedule

Industrial modular Clean Room time:2022/12/08 08:12:25 click:150

What is the clean room schedule? What principles should be followed in preparing a clean room schedule

The construction schedule is based on the construction scheme, according to the specified construction period and the supply conditions of various resources to determine the reasonable construction sequence and construction time of each process and its lap relationship, usually expressed in the form of charts. It is the basis for the formulation of the resource requirement plan and the preparation of the construction preparation plan, and the basis for the control of the construction progress and the completion deadline and other activities. A practical construction schedule can make the construction process proceed in an orderly manner.

What is the clean room schedule? What principles should be followed in preparing a clean room schedule


The construction progress plan expressed in the form of charts reflects the entire construction process from start to completion, and reflects the cooperative relationship between various professional works such as civil engineering, decoration, purification and air conditioning, water, electricity and fire fighting in the construction process of clean room. The scientific preparation of the construction progress plan is conducive to the overall planning of the construction process, the reasonable arrangement of manpower and material resources, is conducive to the technical personnel of each profession and each type of work to have a clear target, and is conducive to the coordination and cooperation of each cross type of work.

Principles for the preparation of clean room construction schedule:

(1) It should be prepared in strict accordance with the construction sequence and adapt to the established construction technical scheme.

(2) Arrange dust work and altitude work first, and do not allow dust work and dust-free work to be crossed.

(3) Attention should be paid to the protection of clean room decoration works.

(4) The installation of the purification air conditioning unit should be able to cooperate with the "air blowing" of the clean room system in time.