How to install the air shower

Industrial modular Clean Room time:2022/11/02 17:58:57 click:189

There is no base and base of air shower equipment, take the base as an example, the equipment is composed of the bottom plate, air shower box (high efficiency filter, fan, nozzle), door, distribution box and so on.

How to install the air shower

One. The installation position shall provide suitable installation space, the ground shall reach the standard level, and the ground level tolerance shall not exceed 3mm.

Two, the bottom plate is generally made of stainless steel, friction resistance and easy to clean. Firstly, the air shower site device is installed in the air shower room;

Three, both sides of the air shower box is fixed on both sides of the chassis, fixed with screws; The air shower box is installed on both sides of the vertical degree, balance degree measurement, to ensure that the two are connected without error; The body is made of ordinary color steel plate, which has a better overall feeling and is consistent with the material of the clean room. It is made of high quality cold rolled steel plate, modern and beautiful.

The four, the next step is to install the door, the wind leaching room before and after the two doors for electronic interlock, using automatic control operation, in the process of using induction automatic blowing rain, two-door locking when blowing rain, when installation will hinge fixed in box body can be on the side of the air shower, hinge is reinforced by three stainless steel hinge, installed to ensure that the door body is completely seamless, There can be no gap between the wall panel and the clean room, and the gap should be sealed.