Clean room purification works clean shed roof installation

Industrial modular Clean Room time:2021/06/17 15:09:27 click:516

Clean room purification engineering clean shed in the actual construction process, the ceiling, wall panels after installation film tearing, cleaning and gluing must be synchronized. Before tearing the film of the general metal panel, a comprehensive inspection should be carried out for the construction of various professions in the clean room, including the purification air conditioning system (including the installation of air conditioners and refrigerators, etc.), the installation of various pipelines, the installation of doors and Windows and the construction and installation of related technical facilities. Clean room air blowing conditions, and make inspection records.

Clean room purification works clean shed roof installation

Construction process description:

(1) Installation preparation, the completion of the preparation work directly affects the construction progress and quality of the installation project.

(2) measurement line setting, measurement line setting is the foundation of clean room decoration construction, especially with a variety of professional installation construction of clean decoration more emphasis on accuracy, and measurement line setting is the construction accuracy can be guaranteed conditions. Due to the construction of many professional, cross construction complex, generally use laser level or a certain accuracy of the level to measure the line. Before playing the ink line, 20-30m cotton thread must be used to check the reference point or reference point; After playing the ink line, it must be checked repeatedly, and relevant signs should be made timely after confirmation. Determine the highest point on the ground, find and determine the highest point on the ground as low as possible with a laser level instrument or a certain precision level, mark the highest point on the ground exactly, and draw a leveling point of 500mm in the center of the column relative to the highest point on the ground.

The installation of the ceiling and wall panels:

Roof installation process is not allowed to use hard tools directly in contact with the color steel plate, so as not to scratch; When moving the metal color steel plate to take gently, not flat lift color steel plate of stainless steel wind shower room; The place of color steel plate should be cleaned and necessary protection measures should be taken; The roof opening should be sealed immediately to avoid scratches or damage to the filling material; Dust production should be strictly controlled and the flow of people in and out should be controlled.